Bump Testing ClO2 Sensors
Overview
G7/G8 Dock can be used to perform ClO2 sensor bump tests. Blackline Safety recommends using Cl2 gas to bump-test the ClO2 sensor in the dock.
Before You Bump Test the ClO2 Sensor
Prior to bump testing a G7 or G8 device equipped with a ClO2 sensor, update your G7/G8 Dock configuration in Blackline Live as follows:
Performing the Bump Test
Once G7/G8 Dock is configured in Blackline Live, set up the dock as follows:
Use Teflon-lined tubing (ACC-FEP-T2) to connect the Cl2 gas cylinder to inlet 1, ensuring the tubing between the dock and the gas cylinder is as short as possible.
Use a stainless-steel regulator or a regulator with a Viton valve seat and seals (ACC‑DFR-V) on the Cl2 gas cylinder.
Before placing a device into the configured G7/G8 Dock, you should:
Ensure that the G7 or G8 device has been switched on, left in fresh air, and has not been bump-tested or calibrated in the last 15- 20 minutes.
Verify that the ClO2 sensor reads 0 ppm. If not, complete a zero of the device in fresh air.
For detailed information on how to bump test or calibrate your device using G7/G8 Dock, refer to the G7/G8 Dock Technical User Manual.